3.9 PAST, ON-GOING AND FUTURE PROJECTS IN GELEPHU
This section gives a summary of the development projects during the Eight and Ninth Five Year Plan periods, along with other long term proposals. This helps us to understand the developmental activities taking place within the town in the past and future.
The Structure Plan includes an Investment Plan for the future infrastructure development. Two Local Area Plans, using land pooling have been completed. They must be technically laid out by competent surveyors. This will involve the demarcation of plots, roads and public lands.
Table 3.7 : Projects listed out during Eighth Five Year Plan
Sr. No. |
Project / Activity |
Description of the Project |
Location of the project in the Municipal limits |
Current stage of project/ Remarks |
1. |
Construction and resurfacing of roads |
- Resurfacing and asphalting of roads in Gelephu town - Construction of road up to Gelephu dratshang - Construction of road up to Fishery Project |
- 347 meters at Purano basti - 1 km at Purano basti |
- Completed - Completed - Completed |
2. |
Construction of footpaths |
- Construction of footpaths in town core |
- |
- |
3. |
Construction of public toilets |
- Out of six toilets, four were not constructed due to lack of funds |
- Near truck parking - Near football ground |
- Completed - Completed |
4. |
Purchase of disposal tractor for solid waste management |
- |
- |
- Not purchased due to lack of funds |
5. |
Construction of drains |
- Storm water drains were constructed near Majhi basti, near football ground, below Gelephu dratshang and, near DPCL fuel station. |
- Football ground : 720 meters - Gelephu Dratshang : 110 meters - Majhi basti : 250 meters - Near DPCL : 375 meters |
- Completed - Completed - Completed - Completed |
6. |
Augmentation of street lights |
- 95 Street lights were augmented. |
- Within town area and along Trongsa highway upto Forest check post |
- Completed |
7. |
Relaying of main pipe line at Lodrai |
- |
- Lodrai |
- Completed |
8. |
Laying of G.I. pipe line distribution network in town |
- |
- |
- |
9. |
Construction of meat stalls and additional vegetable market sheds |
- Construction of two meat stalls with sales counter facility - Construction of one additional vegetable shed |
- Within vegetable market |
- Completed |
10. |
Installation of additional water meters |
- 85 additional water meters were installed |
- |
- Completed |
11. |
Construction of boundary walls along Indo-Bhutan border |
- |
- |
- |
Source: Gelephu Municipal Corporation
Table 3.8 : Projects listed out during Ninth Five Year Plan
Sr. No. |
Project / Activity |
Description of the Project |
Location of the project in the Municipal limits |
Current stage of project/ Remarks |
1. |
Preparation of Master Plan |
- Preparation of Master Plan in order to avoid unplanned developments |
- Gelephu extended areas |
- Undertaken by DUD&ES |
2. |
Survey and demarcation of new Municipal boundary as per Master Plan |
- |
- |
- |
3. |
Land Acquisition |
- Acquiring 20 acres of private lands for developing roads, parks, etc. |
- |
- |
4. |
Construction of new roads and maintenance of existing roads |
- Constructing 10 km of new roads in the extended municipal areas - Maintaining and resurfacing of 7 km of existing road network |
- |
- Only 1.384 km completed - 150 meters completed in town |
5. |
Construction of footpaths |
- Constructing 5 km of footpath along short routes leading to amenities like schools, hospitals, dratshang etc. |
- |
- Under consideration |
6. |
Construction of culverts/drainage |
- Constructing about 10 km of main drain in extended areas to prevent flooding |
- 120 meters along Indo-Bhutan Boundary |
- Completed |
7. |
Construction of public toilets |
- Constructing 6 nos. of pay and use public toilets for public places like bus terminal, cinema hall, dratshang, border check post etc. |
- |
- Under consideration |
8. |
Improving water supply facilities |
- Since the existing sources are inadequate and unreliable it becomes necessary to explore underground water sources for which two bore wells are proposed - Installation of additional pump at infiltration gallery and construction of a reservoir tank (approx 700 m 3)at Lakhitar |
- |
- Under consideration |
9. |
Construction Of additional Market Sheds |
- Constructing additional 10 nos. of market sheds |
- Existing vegetable market |
- Only platforms have been raised for 9 nos. |
10. |
Development of Park / Plaza |
- Developing of one new park and improvement of existing parks in the town center for recreation |
- |
- Under consideration |
11. |
Flood protection works |
- River training works along Mao chhu and Flood protection works along Setikhare chhu and Daula chhu |
- |
- Under consideration |
12. |
Solid waste management |
- Identification of suitable land fill site - Purchasing of Truck for Collection and disposal of solid waste - Purchasing garbage containers / bins |
- |
- Under consideration |
13. |
Vehicle parking and Bus stand location |
- Development of new taxi parking stand - Relocating bus terminal to suitable location |
- 400 sq.m. of taxi parking |
- Completed |
14. |
Augmentation of street lights |
- 100 street lights to be augmented in the extended municipal boundary |
- |
- Under consideration |
15. |
Sewerage project |
- Sewerage system to be laid out in the existing town core and construction of sewerage treatment plant |
- |
- DANIDA project Under consideration |
16. |
Town hall |
- Maintenance and improvement of existing GSA club |
- |
- Under consideration |
17. |
Construction of Stadium |
- Improving the existing football ground |
- |
- Under consideration |
18. |
Re-location of slaughter house |
- |
- |
- Under consideration |
19. |
HRD programs/ Training |
- Various training programs for staff-building |
- |
- |
Source: Gelephu Municipal Corporation
Table 3.9 : Projects listed out on Long-term basis
Sr. No. |
Project / Activity |
Description of the Project |
Location of the project in the Municipal limits |
Current stage of project/ Remarks |
1. |
Construction of National Stadium |
- Proposed by National Youth Council |
- Within Gelephu Industrial Estate |
- Under consideration |
2. |
Gelephu Service Centre |
- Proposed by Ministry of Trade and Industries for locating service-oriented industries |
- Within Gelephu Industrial Estate |
- Under consideration |
3. |
Construction of Dry Port |
- Proposed by Department of revenue and Customs for cargo transactions through Gelephu |
- Behind PWD workshop |
- Under consideration |
4. |
Construction of Bus Terminus |
- Proposed by Road Safety and Transport Authority |
- Within Gelephu Industrial Estate |
- Under consideration |
5. |
River training and flood protection works |
- |
- Along Setikhare Chhu and Mao Chhu |
- Under consideration |
6. |
Construction of International Airport |
- Proposed by Ministry of Informations and Communication |
- Between first and second irrigation channel |
- Under consideration |
7. |
Railway link from Bongaigoan ( India) |
- |
- |
- Under consideration |
Source: Gelephu Municipal Corporation